March 30, 2009 in Istanbul & Caykisla
The Construction Building Permit was issued on 18 May 2009. Power has been brought to the site and a site office erected (see construction photo). Excavation to minus 7 feet has been completed and 18″ of stabilized compacted under-slab backfill has been installed (see construction photos). The earthquake reinforced concrete slab, up to zero elevation is expected to start in three weeks.
Because of a recent change in the bidding law, Ministry Bids for the concrete and steel had to be reissued and are due to be opened and awarded on behalf of the Milli Egitim on 21 June 2009. This represents almost a 3 week delay in the construction completion through no fault of the contractor. Seza Contracting says he will try to make up some of the time. Therefore the steel and concrete placement for the earthquake slab is now expected to be completed by 15 July 2009. Stone floor material and window frames has been selected and approved.
Timeline
- Construction Contract Signed 16 April 09
- Construction Started 1 May 09
- Building Permit Approved & Issued 18 May 09
- Concrete & Reinforcing Steel Bids Delayed to 21 June
- Earthquake Concrete Slab Completes 15 July 2009
- Building Shell Completes 1 September 09
- Substantial Completion expected 15 October 09
- Dedication +/- 30 October 09
There is still a budget short fall of only $18,000 and one “Named Classroom” remaining out of eight. Please be as generous as you can so that all future “Updates” will focus only on construction progress and photos.